Before your particle retest: what to have ready

A retest proves your room still meets its class. Most of the work happens before the tester walks in. Five things decide whether the day runs smoothly.

Reading time
2 min
Published
21 November 2026
The steel sampling funnel of a particle counter on a stand, its clear tube running across a steel benchAI-generated image
The sampling probe: where the counter draws its air at each location.

When the retest is due

ISO 14644-2 sets the longest gap between particle counts. Rooms at ISO 5 and cleaner are counted at least every 6 months. Rooms at ISO 6 to ISO 9 are counted at least every 12 months. Airflow and pressure difference are checked at least every 12 months.

Book the tester a month ahead. A due date that slips is a finding at your next audit.

What to have ready

  1. The class and the state. Agree the class, the particle sizes to count, and the state: at rest (equipment in, no people) or operational. The state changes what you prepare.
  2. The room drawing. Mark the floor area and last year’s sample locations. ISO 14644-1 Table A.1 sets the number of locations from the area.
  3. Your last report. The tester compares results, and an auditor will ask to see both.
  4. Your own logs. Pressure differences, cleaning records and any filter work since the last test. A gap in the logs raises more questions than a high count.
  5. Normal cleaning, not special cleaning. Clean on your usual schedule. The test should show the room as it runs every day.

What to ask the tester

  • The particle counter’s calibration certificate, in date, to ISO 21501-4.
  • The tester’s training record.
  • The number of locations and the air sampled at each one. ISO 14644-1 asks for at least 2 litres and 1 minute per location.
  • A report that names the class, the state, the sizes, every location and every result.

This note sums up ISO 14644-1 and ISO 14644-2 (2015 editions). The full text decides. Buy it from iso.org.

Questions

How long does a particle retest take?

It depends on the floor area and the class. A larger room needs more sample locations, and a cleaner class needs more air at each one. Ask the tester for the count of locations and the time per location before you plan the shutdown.

What happens if one location fails?

The room does not pass until every location is at or under the limit. Find the cause, fix it, and test again. Write down what you changed, so the next audit can follow it.